Trenchless horizontal directional drilling (HDD) works have begun in the Choczewo Municipality for the Baltica 2 project

The sea-to-land HDD crossing is the next stage of the Baltica 2 project – the largest offshore wind farm in Poland, jointly developed by PGE and Ørsted. Thanks to modern HDD technology, the cable lines will connect the offshore and onshore sections of the project while respecting the natural environment and landscape.
The HDD technology allows for precise drilling below the ground surface – without the need for excavation or interference with the beach or dunes. Each of the four boreholes will be approximately 1,200 meters long and drilled at a depth of 20–30 meters below ground level. The works are being carried out by a consortium of Polish companies: ROMGOS Gwiazdowscy and ZRB Janicki.

This is a symbolic moment for the entire project – as the subsea cables are brought ashore beneath the shoreline, the offshore part of the investment meets the onshore part,” said Ulrik Lange, Project Director for Baltica 2 at Ørsted. “Thanks to the use of HDD technology, we can connect these two areas in a way that is safe for the environment and almost invisible from the beach.”

The start of HDD drilling in Choczewo is another important step in the implementation of the Baltica 2 project. It is the least invasive method of cable line installation and does not require any beach closures during construction. This method is safe and performed at a significant depth, which allows us to carry out the works while respecting the landscape and the natural environment,” said Bartosz Fedurek, CEO of PGE Baltica.

After the drilling works are completed – planned for the turn of 2025 and 2026 – installation of the export cables will begin. These cables will deliver the electricity generated by the wind turbines to the mainland.
Impact on the residents of the municipality

Beach access is available via designated pedestrian routes. The developers ask that information signs and instructions from construction staff be respected. All work will be coordinated with local authorities. In the event of temporary changes to traffic organization, advance notice will be provided.

To reduce noise disturbances for residents and tourists, appropriate technical and organizational measures have been implemented – including carefully selected equipment and the location of the works away from residential areas and beaches.
Care for local nature

Before the start of the works, comprehensive environmental surveys were carried out in both the offshore and onshore sections. Based on the collected data, the drilling route was designed to avoid environmentally valuable areas – including the habitat of the smooth snake (Coronella austriaca), a species protected in Poland, as well as the Lubiatowska Dune, considered one of the most valuable elements of the local natural environment. Locations protected under the Natura 2000 network were also taken into account. During construction, qualified personnel will carry out environmental supervision to ensure that all activities comply with the requirements set out in the permits issued for the project.

With a capacity of 1.5 GW, Baltica 2 will be the largest offshore wind farm in the Baltic Sea and will supply clean, renewable energy to approximately 2.5 million households.

Contacts for media:

Beata Głuszcz
Communications Manager
Ørsted Poland
beagl@orsted.com
+48 57 341 25 37

Marcin Poznań
Spokesperson
PGE Baltica
marcin.poznan@gkpge.pl
+48 887 856 620